CV(LOCAL) - FACILITIES CONSTRUCTION

Compliance with Law

The Superintendent shall establish procedures that ensure that all school facilities within the District comply with applicable laws and local building codes.

Construction Contracts

Prior to advertising, the Board shall determine the project delivery/contract award method to be used for each construction contract valued at or above $50,000. To assist the Board, the Superintendent shall recommend the project delivery/contract award method that he or she determines provides the best value to the District. [See CV series generally and CBB(LEGAL) for requirements if federal funds are involved.]

For construction contracts valued at or above $50,000, the Superintendent shall also submit the resulting contract to the Board for approval. Lesser expenditures for construction and construction-related materials or services shall be at the discretion of the Superintendent and consistent with law and policy. [See also CH and CBB(LEGAL)]

Initial Phase

Bidding for District construction projects for which the architect is contracted shall be handled by the architect, who will be responsible for receiving and recording all bonds, deposits, and other documents as required. Performance and pay bonds in the amount of the estimated cost of the project shall be required before contracts for construction are signed.

Change Orders

Change orders permitted by law shall be approved prior to any changes being made in the approved plans or the actual construction of the facility.

Change orders valued at or above $50,000 shall require Board approval. The Superintendent shall be authorized to approve change orders of a lesser amount.

In all change orders, the District's architect shall give a written cost estimate of the proposed change and submit it to the administration. The signature of the Superintendent or designee shall be required before a change order may be executed.

Emergency

When emergencies arise that require an immediate response, the architect may issue a field order when the amount in question is not over $1,000. However, a cost estimate shall be submitted and verbal approval given by the Superintendent or designee before proceeding. The field order shall then be followed by a written change order as indicated above.

Project Administration

All construction projects shall be administered by the Superintendent or designee.

The Superintendent shall keep the Board informed concerning construction projects and also shall provide information to the general public.

Certificates of Payment

The architect shall certify all bills before payment is made and shall issue a certificate of payment outlining the amounts due the contractor. All work shall be performed to the satisfaction of the architect before payment is made. The signature of the Superintendent shall be required on all certificates of payment.

Final Payment

The District shall not make final payments for construction or the supervision of construction until the work has been completed and the Board has accepted the work.